We've also been installing cabinets and finish trim inside,
and are just about ready to turn it over. Move-in day is the week May
10-15, so we've been trying to stay ahead of the furniture. Here you're
looking at Kim Kavatorta's office, and Ran's (below) is next door. As
soon as we finish up, we're off to Pacific
City. We've been working on the handrails and covered entry since
the last picture was taken. The landscapers were on site today (May 6)
and we're about ready to pour the final slab, which will go in the foreground
of this picture.
|
||
![]() |
||
| The picture below is my first attempt at a panorama shot with a new digital
camera. (It's a pretty low-end camera, but it beats the one-hour photo/scanner
combo.) You're looking from left to right about 180 degrees, with the Kiln
building to your left, the Morley House, handicap access ramp and Boyden
Studio at center, and the Centrum Office Building to your right.
On the next page we erected a carved pole in the outdoor classroom area. |
||
![]() |
||
|